Grand Princess

Improvements that happened during an 8 day drydocking.

Grand Princess Cruise Ship lit up at night

Improvements made by Vigor:

  • Made various steel repairs throughout the vessel

  • Removed 3 old AC chillers and installed new ones. A special loading platform was fabrication in advance to accomplish this along with side shell cuts for access. All 3 units were replaced and access sealed in 6 days.

  • A complete renewal of all propulsion shaft bearings.

  • Bow thruster replacement and overhauls

  • Regulatory inspection on all sea valves

  • Seal replacements on rudders and stabilizers

  • Lifeboat and tender davit repair and modifications.

  • Hull coating maintenance and painting of Livery logo on the bow.

  • Assisted Princess subcontractors who revitalized the pools and upgraded the Movie under the Stars screens and equipment.